WB RERA CASE ORDER DATABASE

Date of Order Sections Invoked Complainant & Respondent Summary of Case Download
X-Y-Z Section 6 of RERA Act, 2016; Rule 7 of WBRE Rules, 2027; Section 6 of RERA Act, 2016; Rule 7 of WBRE Rules, 2021. Complainant: Not applicable Respondent: West Bengal Real Estate Regulatory Authority
vs
WBRERA
This order, issued by the West Bengal Real Estate Regulatory Authority (WBRERA), addresses an application for the extension of project registration for the "Natural City Birati" real estate development. The Authority noted that the project's original registration validity had expired on June 30, 2024. The applicant sought an extension, citing significant delays in project completion. The reasons provided for the delay included the prolonged impact of the pandemic, scarcity of labor, supply chain disruptions, and financial strains. After examining the submitted affidavits and documents, the Authority acknowledged the delay and recognized the urgent need for an extension to safeguard the interests of the allottees and facilitate the process of obtaining the Completion Certificate from the competent authority. In exercise of its powers under Section 6 of the RERA Act, the Authority was pleased to grant the extension of the project registration. The validity period has been extended from July 1, 2024, to June 30, 2025. The Authority stipulated that this extension is granted as a Special Case and should not be treated as a precedent for future extension applications. The Secretary, WBRERA, was directed to issue the necessary system-generated certificate accordingly.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: Allottees/Home buyers Respondent: Mahamani Properties Pvt. Ltd.
vs
WBRERA
This order addresses the application for extending the registration of the real estate project, 'Meena Eco-Vista,' which had an existing validity expiring on June 30, 2024. The Authority reviewed the promoter's submissions, which detailed significant delays in project completion. The primary reasons cited for the delay included the impact of the COVID-19 pandemic, resulting in nationwide lockdowns, severe disruptions in the supply chain of construction materials, labor shortages, and general financial instability affecting the industry. After careful consideration, the Authority found that a delay in completion was evident and that an extension was necessary to safeguard the interests of the allottees and facilitate the final handover process. Therefore, exercising powers under the RERA Act, the Authority unanimously granted an extension of the project's registration for a period of 15 months, effective from July 1, 2024, to September 30, 2025. The promoter was directed to formalize this extension by applying in Form E and submitting double the required registration fee. The Authority emphasized that this grant is a special case and not a precedent for future extension applications.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016; Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: N/A Respondent: BENCHMARK DEVELOPERS
vs
WBRERA
This order addresses an application for the extension of the registration validity of a real estate project. The Authority reviewed the request, which sought an extension of 24 months, as the original registration was set to expire on 27.02.2026. The justification for the delay was detailed, citing circumstances beyond the promoter's control. Key grounds included the complete stoppage of construction work due to the COVID-19 pandemic lockdowns and significant delays in receiving necessary access land from the relevant development authority due to pre-existing title disputes. The promoter successfully secured alternate access land only after initiating and concluding legal proceedings in the High Court. After careful consideration, the Authority found that the delay was not attributable to any default or negligence on the part of the promoter. Therefore, exercising powers under Section 6 of the RERA Act, the Authority granted the extension of the project registration validity. The project's completion and delivery date are hereby extended from 28.02.2026 to 28.02.2028 for a period of 24 months. The Authority noted that this extension is granted as a special case and should not be treated as a precedent.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, and Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: None specified Respondent: None specified
vs
WBRERA
This order addresses the application for an extension of the registration period for a real estate project. The Authority noted that the project's registration validity had expired, necessitating an extension to ensure the completion and handover of units to allottees. The Authority examined the reasons provided for the delay, which included the prolonged impact of the pandemic, scarcity of labor, supply chain disruptions, and financial strains. Recognizing that non-completion would severely jeopardize the interests of the allottees—including potential issues with bank disbursements and the ability to obtain home loans—the Authority deemed an extension necessary. In exercise of powers under Section 6 of the RERA Act, 2016, the Authority unanimously granted the extension of the project's registration. The new validity period is set from July 1, 2024, to April 16, 2027. The grant is explicitly issued as a "Special Case" to safeguard the interests of the allottees and facilitate the process of obtaining the Completion Certificate. The Authority directed the issuance of the necessary system-generated certificate reflecting this extended period.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, and Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: Not applicable Respondent: Not applicable
vs
WBRERA
This order addresses an application for the extension of the registration period for a real estate project. The Authority noted that the project's registration validity had expired on March 31, 2024. The Promoter sought a 12-month extension, citing various reasons for the delay, including the prolonged impact of the COVID-19 pandemic (force majeure), delays in obtaining municipal clearances due to NGT complaints, and disruptions caused by general elections. After examining the submitted affidavits and documents, the Authority concluded that a delay in completion exists and that an extension is necessary to safeguard the interests of the allottees and facilitate the issuance of the Completion Certificate. Therefore, the Authority unanimously granted an extension of the project's registration for a period of 12 months, effective from March 31, 2024, to March 31, 2025. The order mandates that the Promoter must formally apply for this extension using Form E and pay double the requisite registration fee. The Secretary is directed to issue the necessary Certificate of Extension (Form F). The Authority emphasized that this extension is granted as a special case and should not be treated as a precedent.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. (Cited multiple times throughout the order.) Complainant: N/A Respondent: N/A
vs
WBRERA
This order addresses an application for the extension of project registration under the Real Estate (Regulation and Development) Act, 2016. The Authority reviewed the request for an extension of the project's validity period, citing significant delays in completion. The justification for the delay was found to be beyond the control of the promoter, primarily attributed to *force majeure* conditions. Key reasons cited for the delay included: 1. The severe impact of the COVID-19 pandemic, leading to lockdowns, labor shortages, and supply chain disruptions. 2. Legal impediments, including the cessation of construction activities by the Pollution Control Board. 3. Mandatory compliance with directives from the National Green Tribunal (NGT), requiring the procurement of Environmental Clearance and Consent to Establish. After careful consideration, the Authority found that the delay was not due to default or negligence. Therefore, the Authority exercised its powers under the RERA Act to grant an extension of the project registration for a period of 39 months (three years and three months). The extension is granted on the grounds of *force majeure* and exceptional legal constraints. The order mandates the promoter to immediately submit the required online application and directs the Secretary to issue the corresponding system-generated certificate. The Authority emphasized that this extension does not affect the rights of the allottees and should not be treated as a precedent.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016. Complainant: N/A & Respondent: N/A
vs
WBRERA
This order addresses the application for an extension of the Project Registration for the 'Surabhi Extension' project. The Authority noted that the project's original registration validity had expired, and despite the promoter's efforts, the construction remains incomplete. The promoter submitted that the delay was due to the customizable nature of the project, which depends heavily on the specific requirements and designs of individual purchasers. After reviewing the submissions, the Authority determined that a delay in completion exists and that an extension is urgently required to safeguard the interests of the allottees and facilitate the process of obtaining the Completion Certificate. Therefore, the Authority exercised its powers under the RERA Act to grant an extension of the Project Registration for a period of **18 months**. The new validity period is set from June 1, 2024, to November 30, 2025. The Authority emphasized that this extension is granted under special circumstances and is not to be treated as a precedent. The promoter is directed to immediately follow up with the necessary online applications to formalize this extension.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016. Complainant: N/A & Respondent: N/A
vs
WBRERA
This order addresses an application for the extension of a real estate project's registration validity under the West Bengal Real Estate (Regulation and Development) Act, 2016. The Authority reviewed the request for an extension of 33 months (two years and nine months), citing the project's inability to complete within the existing validity period. The promoter argued that the delay was not due to negligence but resulted from exceptional circumstances, including the severe impact of the COVID-19 pandemic (lockdowns, supply chain disruptions, and labor shortages) and mandatory legal impediments. Specifically, the delay was attributed to the cessation of construction activities due to directives from the Pollution Control Board and the requirement for Environmental Clearance and Consent to Establish, mandated by the National Green Tribunal. After careful consideration, the Authority found that the delay was unavoidable and urgently required for the project's completion and handover to allottees. Consequently, the Authority exercised its powers under the RERA Act to grant the extension of the project's registration for a period of 33 months, effective from 30.03.2022 to 31.12.2024. The order directs the applicant to submit the necessary online application and mandates the Authority to issue the corresponding System Generated Certificate for the extended period.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, and Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: N/A Respondent: N/A
vs
WBRERA
This order addresses the application for extending the registration of the real estate project, 'Swayam City Phase III,' under the provisions of the RERA Act, 2016. The Authority, after considering the submissions, found that the delay in project completion was not attributable to any default or negligence on the part of the promoter. The primary reasons cited for the delay were deemed to be *force majeure* conditions, specifically: 1. The severe disruptions caused by the COVID-19 pandemic and subsequent lockdowns. 2. Significant legal and regulatory impediments, including a status quo order issued by the National Green Tribunal (NGT) and the mandatory requirement for Environment Clearance (EC) and Consent to Establish (CTE). Given that the extension is crucial for the completion certificate and protecting the interests of allottees, the Authority exercised its power under Section 6 of the RERA Act. Consequently, the registration of the project has been granted an extension of **33 months (2 years and 9 months)**, effective from 30.03.2022 to 31.12.2024. The order emphasizes that this extension is granted as a special case and should not be treated as a precedent.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: None Respondent: None
vs
WBRERA
This order addresses an application for the extension of project registration under the Real Estate (Regulation and Development) Act, 2016. The Authority reviewed the request, noting that the project’s previous extension period expired on August 30, 2024. The core justification for the extension lies in the inability to secure the final Completion Certificate by the stipulated deadline. The Authority acknowledged that delays were attributed to post-pandemic economic slowdown, labor shortages, and the finalization of common facilities (such as landscaping and recreational areas). After examining the submitted affidavits and supporting documents, the Authority concluded that an extension is necessary to safeguard the interests of the allottees and facilitate the final handover process. Therefore, exercising powers under Section 6 of the RERA Act, the Authority unanimously granted an extension of the project registration. The project is granted a new validity period from August 31, 2024, to August 30, 2025. The order emphasizes that this extension is granted as a special case and should not set a precedent for future applications.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016. Complainant: Allottees (Implied, as the interest of the allottees is mentioned as being seriously affected) Respondent: Devaloke Developers Limited
vs
WBRERA
This order addresses an application for the extension of the project registration validity for a real estate development project. The Authority reviewed the promoter's request, which sought an extension of 13 months and 2 days. The promoter submitted detailed justifications for the delay, citing several factors beyond their control. These included the prolonged impact of multiple Covid-19 waves, resulting labor and supply chain disruptions, financial constraints, delays in local infrastructure development, and, most significantly, multiple legal injunction orders imposed by competent courts, totaling a substantial period of delay. After careful consideration, the Authority concluded that the delay in project completion was not attributable to any default or negligence on the part of the promoter. Therefore, exercising powers under Section 6 of the RERA Act, 2016, the Authority granted the extension of the project registration for a period of 13 months and 2 days, effective from 29.11.2023 to 31.12.2024. The extension was granted on the grounds of *force majeure* (Covid-19) and legal injunctions. The order emphasizes that this grant is a special case and should not be treated as a precedent.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: None Respondent: CHARLES COMMERCIAL PVT' LTD
vs
WBRERA
This order addresses an application for the extension of a registered real estate project. The Authority noted that the project's registration validity had expired, necessitating an extension to ensure the completion and handover of units to allottees. The Promoter submitted a detailed affidavit citing multiple reasons for the delay, including the prolonged impact of the pandemic, severe disruptions in the supply chain and labor availability, financial strains, and structural depreciation. The Promoter emphasized that a valid registration is crucial for obtaining the final Completion Certificate. After careful consideration of the submissions, the Authority determined that a delay in completion was evident and that an extension was necessary to safeguard the interests of the allottees. Therefore, the Authority exercised its powers under the RERA Act to grant the extension of the project's registration. The project is granted an extension period from October 1, 2024, to June 30, 2026. The order specifies that this extension is granted as a special case and should not be treated as a precedent for future applications.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016. (Cited multiple times throughout the order.) Complainant: N/A Respondent: N/A
vs
WBRERA
This order, issued by the West Bengal Real Estate Regulatory Authority (WBRERA), addresses an application for the extension of project registration for a real estate development. The Authority noted that the project's registration validity was set to expire on April 30, 2025. The Promoter sought an extension until April 29, 2026. The Promoter cited various reasons for the delay, including the prolonged adverse effects of the COVID-19 pandemic, which disrupted the global economy, supply chains, and market sales velocity. After a thorough examination of the submitted affidavits and documents, the Authority concluded that a delay in completion exists and that an extension is urgently required to safeguard the interests of the allottees and facilitate the handover process. Therefore, the Authority unanimously granted the extension of the project registration for a period commencing from May 1, 2025, to April 29, 2026. The order explicitly states that this extension is granted as a "Special Case" and should not be treated as a precedent for future applications.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016. Complainant: None & Respondent: None
vs
WBRERA
This order addresses an application for the extension of the registration validity of a real estate project. The Authority noted that the project's previous extension expired on February 7, 2023, and the promoter sought a further extension of 14 months. The promoter justified the delay by citing *force majeure* conditions, primarily the COVID-19 pandemic. Key reasons provided included country-wide lockdowns, severe disruptions in the supply chain of construction materials, labor shortages, and financial difficulties affecting the timely payment of installments by allottees. After reviewing the submissions, the Authority concluded that the delay in project completion was not attributable to any default or negligence on the part of the promoter. Therefore, exercising powers under the Real Estate (Regulation and Development) Act, the Authority granted the extension of the project's registration for a period of 14 months, effective from February 8, 2023, to April 7, 2024. The order stipulates that this extension is granted as a special case and should not be treated as a precedent. The promoter is directed to immediately submit the required online application, and the Authority Secretary is directed to issue the corresponding system-generated certificate.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, and Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: Ambuja Neotia Hotel Ventures Limited & Respondent: West Bengal Real Estate Regulatory Authority
vs
WBRERA
This order addresses an application for the extension of the registration validity for the real estate project, 'Ganga Kutir Residency Limited Edition.' The Authority noted that the project's registration validity had expired, and the Promoter sought a significant extension, citing the customizable nature of the project and delays related to individual buyer requirements and occupancy orders. After careful consideration of the submissions, the Authority determined that an extension was necessary to safeguard the interests of the allottees and facilitate the completion of the project and the obtaining of the requisite completion certificate. Consequently, the Authority exercised its powers under the RERA Act to grant an extension of the project's registration for a period of **18 months**. This extension is effective from June 21, 2023, to December 20, 2024. The order emphasizes that this extension is granted as a special case and does not affect the rights or interests of the allottees. The Promoter is directed to immediately submit a formal online application for the extension, and the Authority is directed to issue the corresponding system-generated certificate.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: RAMKRISHNA ENTERPRISE Respondent: West Bengal Real Estate Regulatory Authority
vs
WBRERA
This order, issued by the West Bengal Real Estate Regulatory Authority (WBRERA), addresses a request for an extension of the project's registration period. The Authority reviewed the application, noting that the project's original registration validity had expired on December 22, 2022. The applicant argued that completion was delayed due to extraordinary circumstances, primarily citing the severe impact of the COVID-19 pandemic, subsequent nationwide lockdowns, supply chain disruptions, and financial difficulties in the real estate sector. After careful consideration of the submitted affidavits and supporting documents, the Authority determined that an extension was urgently necessary to safeguard the interests of the allottees and facilitate the completion and handover of units. In exercise of powers under Section 6 of the RERA Act, 2016, the Authority unanimously granted an extension of the project's registration. The validity period has been extended from December 22, 2022, to May 31, 2025. The Authority emphasized that this extension is granted as a special case to protect the allottees' interests and is not to be treated as a precedent for future extension claims.
X-Y-Z Section 6 of the Real Estate (Regulation & Development) Act, 2016. Complainant: West Bengal Real Estate Regulatory Authority Respondent: Central Government Employees Welfare Housing Organisation
vs
WBRERA
This order addresses an application filed under the Real Estate (Regulation & Development) Act, 2016, seeking an extension for the registration validity of a specific housing project. The developer sought an extension because the project was not yet commenced and the original registration was set to expire on December 31, 2025. The justification for the delay included a need to revise the sanctioned plan due to low demand for certain units, and the adverse impact of the second wave of the COVID-19 pandemic, which the developer argued was beyond their control. After careful consideration of the submissions and supporting affidavits, the Authority found that the delay in completion was not attributable to any default or negligence on the part of the developer. Therefore, exercising powers under Section 6 of the RERA Act, the Authority granted an extension of the project's registration validity. The project's validity has been extended for a period of twelve months, from December 31, 2025, to December 30, 2026. The Authority directed the relevant secretary to issue the necessary Extension Certificate.
X-Y-Z Section 6 of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the West Bengal Real Estate (Regulation and Development) Rules, 2021. Complainant: Allottees/Home buyers Respondent: Mata Di Real Estate
vs
WBRERA
This order addresses the application for an extension of the registration of the real estate project, ‘Chandana Apartment,’ whose original validity had expired. Following a detailed hearing, the Authority considered the promoter’s affidavit, which explained the delay in completion due to financial stringency. The promoter requested an extension until June 15, 2025, to complete remaining works, including plastering and finishing touches, and facilitate the handover of units to allottees. Finding that a delay existed and that an extension was crucial to safeguard the interests of the home buyers and obtain the necessary Completion Certificate, the Authority unanimously granted the extension of the project’s registration. The extension is granted for the period spanning from July 10, 2022, to June 15, 2025, and is explicitly designated as a Special Case, not to be treated as a precedent. Crucially, the grant is conditional: the promoter must immediately submit a formal online application, deposit fees equivalent to twice the original registration fees, and the Authority will then issue the official Extension Certificate.
X-Y-Z Section 6 of RERA Act, 2016; Rule 7 of WBRERA Rules, 2021; Category B_3 of the New Extension Regulation (No. 921-RERA). Complainant: SAHA ENTERPRISE & Respondent: West Bengal Real Estate Regulatory Authority
vs
WBRERA
This order addresses an application for the extension of project registration for a real estate development. The Authority noted that the project's original registration validity had expired, and the promoter sought an extension due to delays in completion. After reviewing the submitted affidavits and supporting documents, the Authority found that an extension was necessary. Consequently, the Authority unanimously granted the extension of the project registration for a period from October 8, 2025, to October 7, 2026. Crucially, the extension is subject to several strict conditions and the imposition of a penalty of Rs 12,160/- for contravention of the relevant RERA regulations. To formalize the extension, the promoter must first deposit the penalty amount. Furthermore, the promoter is mandated to submit a detailed Work Milestone via a Notarized Affidavit within 15 days. Ongoing compliance requires the submission of quarterly updates and detailed work milestones every 90 days thereafter. The Authority reserves the right to conduct unannounced inspections, and any misrepresentation or discrepancy will lead to stringent action, including the revocation of the extension.
X-Y-Z Section 14(2)(ii) RERA Act, 2016; Rule 16(5) WBR Rules, 2021; Section 3(1) RERA Act, 2016; Section 4(2)(1)(D) RERA Act, 2016; and Section 3(a) WBR Rules, 2021. Complainant: N/A & Respondent: N/A
vs
WBRERA
This order, issued by the West Bengal Real Estate Regulatory Authority (WBRERA), grants approval for modifications and alterations to the sanctioned plan of the project, HANUMAN COMPLEX, under Section 14(2)(ii) of the RERA Act, 2016. The Authority reviewed the application for changes based on a revised sanctioned plan. Crucially, the Authority noted that since the project currently has no allottees, the statutory requirement for obtaining prior written consent from two-thirds of existing allottees is not applicable. Consequently, the Authority allowed the proposed changes, which involve significant revisions to the project's land and built-up areas, including adjustments to both residential and commercial components. However, the approval is conditional. The Applicant is mandated to remit a registration fee of Rs. 30,230/- for the commercial land area. Upon receipt and verification of the payment proof, the Authority shall issue the Modified Certificate and update the necessary details on the WBRERA website.